Sunday, December 6, 2009

Mill Train in Position on Mezzanine

Our Malt Hopper (the table structure in foreground) is now in place with the screw conveyor (the white tube) taking the malt up to the Mill on the mezzanine floor. The BIG BLUE VALVE is the gas main supply.
Upstairs the red Mill crushes the grain and the next bendy white tube conveyor takes it up to the top of the Grist Case with its 1 tonne capacity. When we mash in (mixing the grist with hot water in the mash tun) there is a third screw conveyor to take the grist from the grist case bottom to the Mash Mixer on top of the Mash Tun.
Most of the major construction work is complete in the new brewery but as I've said before, there is still plenty to do - steam boiler, lagging of pipework (all 2.7 kilometres of it!), refrigeration, electrics, motors and pump refurbishment, let alone bringing over the existing fermenters and conditioning tanks from the present brewery....